Here are some pictures of a recent dry chiller removal and replacement installation undertaken by Conair (UK) Ltd at a Central London location.

The new unit (shown being craned into position) weighs in at approximately 1.5 metric tonnes.

The proximity of the active South West Main Line meant that a full liaison was maintained with Network Rail and road closure times were kept to a minimum through careful planning and thorough management.

The critical nature of the application meant that the replacement of existing equipment had to be achieved within two days.
As it happens, Conair (UK) Ltd’s workforce enabled beneficial operation of the new equipment to be available by the end of day one!

The replacement unit will provide the client with great energy saving benefits over the redundant previously installed equipment, as well as assuring future reliability.

If you are looking to improve the sustainability of your building engineering services equipment, or just need some helpful advice, get in touch with us now, using the “Contact Us” tab, or by calling our Sales and Support number on 01702 544344.